The regulators, on appeal â one search. Track TDSAT and APTEL case status for telecom, broadcasting and electricity appeals â free on eCourtsIndia: https://blogs.ecourtsindia.com/2026/06/13/tdsat-aptel-case-status-search-ecourtsindia/
seen from United States
seen from United States
seen from United States
seen from United States
seen from United States

seen from United States
seen from United States

seen from United States

seen from United States

seen from United States

seen from Malaysia
seen from United States

seen from United States
seen from China
seen from United States
seen from United States
seen from United Kingdom

seen from United States
seen from China

seen from United States
The regulators, on appeal â one search. Track TDSAT and APTEL case status for telecom, broadcasting and electricity appeals â free on eCourtsIndia: https://blogs.ecourtsindia.com/2026/06/13/tdsat-aptel-case-status-search-ecourtsindia/

Anya is live and ready to show you everything. Watch her strip, dance, and perform exclusive shows just for you. Interact in real-time and make your fantasies come true.
Free to watch ⢠No registration required ⢠HD streaming
Protracted appellate litigation structurally deters mid-scale generators from agile market participation
Mid-scale private generators must navigate multi-year jurisdictional appeals regarding fractional megawatt capacities, a legal mechanism that locks up operational bandwidth. Short-term green markets bear the consequence, starved of the liquidity these generators could otherwise provide to the broader exchange.
The Electricity Act of 2003 established the Appellate Tribunal for Electricity (APTEL) to resolve disputes between generators and state regulators. However, the tribunal's procedural timeline allows contract disputes over minor capacity ratings to drag on for decades. This framework legally forces independent generators to prioritize litigation survival and legal overhead over active participation in real-time or term-ahead power exchanges, sidelining the exact flexible capacity needed to balance the grid.
A Judgment / Appeal Order from the Appellate Tribunal for Electricity, dated 16th March, 2026, officially dismisses an appeal over a localized 18 Megawatt (MW) capacity reduction for a Power Purchase Agreement originating in 2007. In contrast, the Indian Energy Exchange GTAM_Trade Details for 16-03-2026 logs a symptomatic clearing volume of just 0.73 MWh in specific trading blocks. A 19-year legal battle over 18 MW acts as a tracer dye, proving that the appellate framework structurally traps the mid-scale capacity required to deepen the illiquid 0.73 MWh green term-ahead market.
Legal authorities argue that statutory due process cannot be accelerated simply because the megawatt capacity in dispute is small, maintaining that all contractual appeals require rigorous judicial scrutiny to ensure regulatory fairness. While legal equity is necessary, utilizing a 19-year supreme appellate process to resolve an 18 MW contract dispute structurally paralyzes the commercial agility of mid-scale power producers.
The Ministry of Power must establish a fast-track arbitration mechanism with a strict 180-day resolution limit for all capacity disputes under 100 MW. Without this regulatory reform, mid-scale independent power producers will remain legally stranded in appellate courts rather than actively participating in the short-term energy markets.
For more such stories, go to Click Here
APTEL Ripple Hits Tariffs: CERC Reworks Fiber-Optic Fees Across Three Periods
In a major retrospective correction, the Central Electricity Regulatory Commission (CERC) has reopened and recomputed tariffs for PGCILâs Northern Region ULDC fiber-optic communication assets after the Appellate Tribunal for Electricity (APTEL) condoned earlier disallowed time overruns.
APTELâs 2022 judgment (Appeal No. 15 of 2016) held that construction delays on two key assets were the consequence of external factors â including delayed participation by UPPTCL and PTCUL, and unavoidable fog-related safety constraints. With these delays no longer attributable to PGCIL, CERC rebuilt the capitalisation figures from the date of commercial operation (COD), triggering a full recalibration of tariffs across multiple regulatory windows.
The outcome is a rare multi-period reset: tariff adjustments across 2009â14, 2014â19, 2019â24, and a revised opening capital base for the ongoing 2024â29 block.
Fiber-Optic Assets at the Core of the ULDC Backbone
The assets under consideration are part of the Northern Region ULDC modernisation programme, which replaced ageing microwave links with a modern fiber-optic communication system using OPGW, underground cable, aerial cable, SDH equipment and a network management system.
Assets 1â4 are classified as system-operation related communication assets under Section 28(4) of the Electricity Act. Asset-5, however, is treated as a transmission element under Section 62 read with Section 79(1)(d), bringing it under a different tariff methodology. CERCâs order therefore spans both families of regulatory treatment.
IDC and IEDC Reinstated â Capital Cost Reset from COD
A central consequence of APTELâs ruling is the reinstatement of Interest During Construction (IDC) and Incidental Expenditure During Construction (IEDC) for Asset-2 and Asset-3. These amounts were previously cut when CERC refused to condone delays back in 2015.
By restoring IDC/IEDC and adding them back to the COD capital cost, CERC altered the foundational asset value used in multiple tariff blocks. Even though the additions themselves are modest, the regulatory impact is significant because all subsequent years depend on the opening capital base.
2009â14: Minor Fee Corrections, Major Structural Shifts
CERC has recomputed fees and charges for 2012â13 and 2013â14 for the affected assets. The adjustments range from âš0.05 lakh to âš2.47 lakh â numerically small, but critical in shaping the capital recovery trajectory.
These revised figures become the opening capital cost for 2014â19, which in turn feeds into 2019â24 and sets the stage for 2024â29. What appears to be a modest historical correction ends up reshaping three tariff cycles.
True-Ups Reworked for 2014â19 and 2019â24
With the corrected capital base flowing forward, CERC recalculated:
normative loanâequity balances
depreciation and capital-recovery factors
interest on loan based on weighted average rates
post-tax RoE at 15.5%
interest on working capital
This ensures that beneficiaries neither overpay nor underpay relative to the adjusted capital structure.
2024â29: New Period, Clean Opening Balance
For the ongoing control period, CERC has approved fresh fees and charges for communication assets and transmission tariff for Asset-5 under the 2024 Tariff Regulations.
The Commission applied updated O&M trajectories, revised benchmark rates for working capital, and the new tax/gst pass-through framework. Standard regulatory permissions to PGCIL â including income tax recovery, filing for security/insurance expenses, and claiming capital spares â have also been reaffirmed.
A Corrective Exercise with Limited Financial Shock
Despite the years being re-opened and recomputed, the financial impact on beneficiaries is limited: small upward adjustments in 2012â14 and modest realignments in later periods.
But the regulatory cleanup is substantial. CERC has now aligned all periods with APTELâs findings, corrected historical inconsistencies, and ensured the ULDC fiber networkâs asset values reflect actual allowable capitalisation from COD through 2024â29.
A Precedent for Future Delay-Related Appeals
The order reaffirms an important regulatory principle: where delays stem from beneficiary-driven or uncontrollable factors, the CTU cannot be penalised. It also shows how APTELâs decisions cascade into tariff arithmetic many years down the line â affecting both historical true-ups and future tariff frameworks.
For the Northern Regionâs communication backbone, the tariff architecture is now consistent, corrected and transparent â exactly as APTEL intended.
For more https://www.energylineindia.com/
Regulatory Transition Is Not a Defence: APTEL Draws a Clear Line
APTELâs latest ruling sends a powerful message to generating utilities: once new regulations come into force, compliance must shift fully to the updated framework. Transition periods may be challenging, but they cannot be used as a defence for procedural lapses.
What RRVUNL Argued
RRVUNL claimed that several units including Kota TPS Unit-7, Suratgarh TPS Unit-6, and Chhabra TPS Units 1 ,2 were conceived under the 2009 regulations but reached COD under the 2014 regime.
The utility said this created a âregulatory twilight zoneâ where final capital expenditure and closing activities couldnât neatly match the 2014 cut-off provisions.
Why APTEL Rejected the Argument
APTEL held that once the 2014 Regulations became effective, all tariff petitions â even for ongoing projects â had to align with the new framework.
Key points APTEL highlighted:
No automatic exemption during regulatory transition
Compliance is a continuous responsibility
Documentation must match the prevailing code
Relaxation Clauses Not Automatically Applicable
RRVUNL cited Regulation 2(17), its proviso for extensions, and Regulation 94 (relaxation powers). However, APTEL found that:
RRVUNL never sought an extension formally
No evidence was submitted showing delays beyond control
Relaxation powers must be invoked through a reasoned petition
In short: exceptions cannot be claimed retroactively.
Tribunalâs Core Principle
Regulatory transition does not suspend regulatory compliance.
Once a new tariff regulation is notified:
Cut-off dates must be respected
Documentation must be aligned
Tariff claims must meet updated procedural requirements
Legacy project timelines do not override current obligations.
What This Means for the Power Sector
This ruling strengthens regulatory accountability:
No automatic grandfathering of past projects
No retrospective condonation without evidence
Stricter scrutiny of capital expenditure claims
Greater procedural discipline expected across utilities
It also reflects a consistent trend across regulatory bodies and tribunals in India.
Fore more https://energylineindia.com/
Status Quo Wins Over Empirical Re-Design
Gujarat keeps the 7â11 AM To U morning peak not because the data proves a peak exists, but because removing it risks creating one.
APTEL wanted a clean, fresh, empirical re-evaluation of the morning peak classification.
Because when you look at load data in Gujarat 7â11 AM does not display a conventional peak.
So logically: if there is no peak, why keep the premium?
What GERC argued instead
The morning curve is flat because the penalty exists. The price signal itself is suppressing the possible peak.
If you remove that signal the peak may reappear.
This is stability-by-policy not natural equilibrium of consumption behaviour.
PGVCLâs framing
daily load curve in Gujarat is shaped over 20 years of ToU + agriculture feeder scheduling
HT industrial consumers have already shifted what can be shifted
stability is artificially engineered therefore cannot be treated as âevidenceâ against the peak
The Meghraj study angle
While the study wasnât written to test the 7â11 AM block directly GERC used it as contextual validation.
Small load shifts matter. They prevent certain network reinforcements + avoid costlier procurement in stressed hours.
Industry argued the opposite
If the data doesnât show a peak â the premium is legacy inertia.
GERC rejected that. Continuity wins.
Final result
Morning peak stays
ToU rates FY 2016â17 unchanged
No new empirical study ordered
The deeper India tariff reality
Once a demand smoothing tool embeds inside the system⌠unwinding becomes politically + grid-operationally high risk.
The price of stability â is postponing discovery.
We donât know if the 7â11 AM peak is real anymore because we refuse to test it.
For more
For reference purposes the website carries here the following tenders: â˘Tender for supply of various electrical AC/DC MCB\'s ins

Anya is live and ready to show you everything. Watch her strip, dance, and perform exclusive shows just for you. Interact in real-time and make your fantasies come true.
Free to watch ⢠No registration required ⢠HD streaming
 Wind power developer
The Appellate Tribunal for Electricity (APTEL) has rejected the review petition filed by IPCL, confirming its December 2024 order that prioritises wind energy first, then STOA, and finally PGVCL supply. The dismissal removes ambiguity for Gujaratâs wind power developer ecosystem.
The bench ruled that no âself-evident errorâ existed and reiterated that review power is limited to glaring omissions. For every wind power developer, this means energy settlements will continue under the WTG-first rule, with surpluses valued at 85 %.
The judgment underscores that commercial grievances cannot reopen concluded interpretations. It strengthens investor confidence in wind power developer frameworks where sequencing stability governs return calculations and compliance.
More verified regulatory insights on EnergylineIndia.com, Indiaâs independent energy-intelligence platform tracking wind power developer and renewable policy
trends,Wind Power Developer, Energyline India, APTEL, Gujarat Power, WTG, STOA, PGVCL, Renewable Energy India, Electricity Tribunal, Power Sector News.
Gujarat wind-energy priority clause survives second challenge
The 2010 WTG-first principle and 85% deemed-sale rule remain valid after the review dismissal. Utilities can continue settlement under the 2024 hierarchy.
Tribunal affirms earlier sequencing order
The Appellate Tribunal for Electricity (APTEL) has dismissed Review Petition No. 11 of 2025 filed by Investment & Precision Castings Ltd (IPCL) against its 3 December 2024 judgment in Appeal 339 of 2018. That earlier judgment had re-sequenced Gujaratâs multi-source energy accounting, giving first priority to wind-turbine generation (WTG), followed by Short-Term Open Access (STOA) energy, and finally distribution supply from PGVCL.
With the latest order dated 3 November 2025, the bench of Mr Virender Bhat (Judicial Member) and Ms Seema Gupta (Technical Member-Electricity) has reaffirmed the 2010 WTG-first clause and the 85 % deemed-sale pricing rule for monthly surplusesâclosing a multi-year challenge.
Consumerâs banking-loss argument rejected
IPCL alleged a financial loss of âš 30.65 lakh in denied six-month banking benefit and âš 3.37 lakh from curtailed deemed-sale credit. The petitioner claimed APTELâs 2024 formula ignored historical wheeling agreements (2006 and 2010) and the 2002 banking policy, terming it a âmanifest error.â
The Tribunal disagreed, holding that the petition sought to substitute methodology rather than correct a self-evident mistakeâand therefore amounted to an appeal in disguise. Only patent or apparent errors qualify for review, not interpretive disagreements.
Law of review strictly applied
Citing Order XLVII Rule 1 CPC and Supreme Court precedentsâKamlesh Verma v. Mayawati (2013) and S. Madhusudhan Reddy v. V. Narayana Reddy (2022)âthe Tribunal reiterated that review powers extend solely to âglaring omissions or mistakes apparent on the record.â Erroneous decisions must be corrected through appeal, not re-hearing. Finding no fresh evidence or self-evident error, the bench declined jurisdiction to reopen the case.
Outcome and implications
APTEL concluded that no patent mistake or omission existed in its December 2024 ruling, dismissing the review petition without costs.
For Gujaratâs distribution licensees, the decision secures continuity of the 2024 settlement hierarchyâ 1ď¸âŁ WTG energy first (2010 WTG before 2006 WTG, surplus sold at 85 %), 2ď¸âŁ then STOA energy, 3ď¸âŁ and finally PGVCL supply.
For captive consumers, it clarifies that banking-benefit or tariff-valuation disputes must be raised before the regulator or via statutory appeal, not through review.
Final takeaway
With Review Petition 11 of 2025 now disposed of, APTELâs wind-energy priority formula attains procedural finality unless overturned under Section 125 of the Electricity Act 2003 before the Supreme Court. The case underscores that review jurisdiction in Indiaâs power-sector tribunals is governed by procedural precision, not equity or commercial impact. For more https://www.energylineindia.com/
The National Solar Energy Federation of India (NSEFI) argued that Tamil Nadu should be accountable for the energy supplied