Drainage Information to submit to council for approval:
Drainage Information to submit to council for approval:
 Requirements:
I)Â Â Â Â Â Â Â Â Â Â Â Â Â Information required on the plan
i)Â Â Â Â Â Â Â Â Â Â Â Â Â Overall catchment area
ii)Â Â Â Â Â Â Â Â Â Â Â Â Location of internal drainage, pipe size material and grade
iii)Â Â Â Â Â Â Â Â Â Â Pit details, showing dimension, surface
iv)Â Â Â Â Â Â Â Â Â Â Location of storm water outlet
v)Â Â Â Â Â Â Â Â Â Â Â Â Details of all internal connections that are connected up to the OSD system before leaving site
II) Design parameters from a city council in Melbourne
           Residential Development:
-Â Â Â Â Â Â Design storm period of 5 ARI
-Â Â Â Â Â Â Rainfall intensity based upon Australian Runoff 1987
-Â Â Â Â Â Â Coefficient runoff: pervious area 0.2, impervious area 0.8
Commercial Development
-Â Â Â Â Â Â Design storm period of 10 ARI
-Â Â Â Â Â Â Rainfall intensity same as for residential development
-Â Â Â Â Â Â Coefficient runoff: pervious area 0.1, impervious area 0.9
II)Â Â Â Â Â Â Â Â Â Â Â Prior to construction, the developer is to:
-Â Â Â Â Â Â Obtain approvals from relevant authorities
-Â Â Â Â Â Â Undertake all surveys
-Â Â Â Â Â Â Dial before you dig, and ensure all service information is present
-Â Â Â Â Â Â Present professional drafts